DPU Sets Procedural Schedule in Cape Wind Docket

July 14, 2010

in Regulatory Affairs,Renewable Energy,Utility News

The Massachusetts Department of Public Utilities (DPU) has issued its Procedural Schedule in Docket No. 10-54: Review of Proposed Long-Term Power Purchase Agreement Between Massachusetts Electric Company and Nantucket Electric Company d/b/a National Grid and Cape Wind Associates, LLC.

PROCEDURAL SCHEDULE

Pursuant to 220 C.M.R. § 1.06(6), the following procedural schedule will apply:

July 16, 2010 – Intervenors provide notice of intent to file testimony
July 23, 2010 – Attorney General comments due
July 23, 2010 – Intervenor pre-filed direct testimony due
August 12, 2010 – Pre-hearing conference
August 18, 2010 – Discovery closes
August 25, 2010 – Final discovery responses due
August 30 – September 17, 2010 – Evidentiary hearings
TBD – Simultaneous initial briefs due
TBD – Simultaneous reply briefs due

For the full Procedural Schedule, Service List, and Ground Rules applicable in this proceeding, click HERE.



Related Posts:

  1. NGRID Expected To File Cape Wind PPA Today
  2. Recent Study Shows Additional Hidden Costs of Cape Wind
  3. MA DPU Opens POR Program Docket
  4. MA ENB Week In Review: 6/4/10
  5. DOI Approves First U.S. Offshore Wind Farm

Leave a Comment

*

Previous post:

Next post:


.
MA ENB Blackcard
.
.
Buy.com MA ENB
.

HEADLINES | UTILITIES | RENEWABLES | GOVERNMENT | REGULATORY | SMART GRID | BLOG | ARCHIVES | TWITTER | SITEMAP

. .
.

CALIFORNIA | CONNECTICUT | DELAWARE | ILLINOIS | MAINE | MARYLAND | MICHIGAN

.

NEW HAMPSHIRE | NEW JERSEY | NEW YORK | OHIO | PENNSYLVANIA | RHODE ISLAND | TEXAS

.
.

© 2010 | Energy News Board | Built on WordPress | Spread the News

.